Over 1800 outlets with four category 6 connections
14 telecomunication rooms connected with 24 strands of 10 gig fiber.
ITRACS installation
18 month project. All work performed at night. Worked around existing network until cutovers (by floor). No loss of existing network during project. All cutovers were on time.